Four basic steps are used in an abc system. list the proper order of these​ steps, which are currently scrambled​ below:

a. identify the primary activities and estimate a total cost pool for each.

b. allocate the costs to the cost object using the activity cost allocation rates.

c. select an allocation base for each activity.

d. calculate an activity cost allocation rate for each activity.

Respuesta :

First Identity the primary activities
Then goes select an allocation
Followed by calculating an activity
And finally allocate the costs

Hope this helps