30 men can do a piece of work in 40 days .how long it take to complete the work if 5 men were reduced​

Respuesta :

kandelhira20
kandelhira20 kandelhira20
  • 23-02-2020

Answer:

it is from unitary method

men days

30 40

25 let(x)

now from indirect variation

25×x = 30×40

25x= 1200

x=1200÷25

x=48

so there were 48men to complete the work

Answer Link

Otras preguntas

Can someone plz help me with this one problem plzzzzz!!!
Help me plzzzzzzzzzzzzzzzzzz
Jack had four Snicker bars and 8 Mars bars. He randomly chose a piece of candy, ate it, then chose another. What is the probability that both candy bars were Sn
Louis wants to buy skis that have a regular price of $328. They have been marked down 25% off the regular price. Louis calculates the new total price including
Jayden buys stickers for $2 each and marks up the price by 55%. How much profit does Jayden make from each sticker sold?
PLS HELP ME! I WILL GIVE BRAINLIEST!
Classify the triangle as acute, right, or obtuse based on the side lengths of 8, 11, and 14.
The Question Is In The Image.
will mark brainliest if you answer A brand of uncooked spaghetti comes in a box that is a rectangular prism with a length of 10 inches, a width of 3 inches, an
PLS HELP! I WILL GIVE BRAINLIEST!!!!!!! Identify the Mesopotamian civilization on the map.