30men can finish 1/7of a work in 2days.18men will do othe remaining work in ?

Respuesta :

chumxo chumxo
  • 24-09-2016
7/7-1/7=6/7 is the rest of work
1/7 work takes 2days
6*1/7=6/7 work takes 6*2days=12days
30 men takes 12 days to finish the rest of work (6/7)
18 men takes 18*12/30= 7.2days
Answer Link

Otras preguntas

1/6 of a ship's crew are engineers, 1/4 are stewards and the rest are soldiers. if there are 48 crew members in all, how many sailors are on the board of the sh
which one of the following sentence contains a predicate adjective
What was good abt technology in 1930
If the supplement of an angle is two-third of itself ,then its supplement is
what is 3xY=4w solve for y in formula transformation
There are some cases where distance time graph of a particle is vertical . So could you please tell me when it is possible????
What was the Battle of Wounded Knee?
what 3 numbers multiply to get 63?
what is a group of snakes called?
What was good abt technology in 1930