Differentiate between the scheduling techniques known as CPM and PERT

Respuesta :

foreverronneshia foreverronneshia
  • 25-03-2022
PERT is for Program Evaluation and Review Technique, whereas CPM stands for Critical Path Method. PERT is used to manage unpredictable activities, whereas CPM is used to manage predictable ones. PERT is concerned with events, whereas CPM is concerned with activities.
Answer Link

Otras preguntas

Which of the following would make a good thesis statement on the topic of yearly driving tests for the first five years after getting a license? A. Would the ge
state the slope of the line y = 3x -7
PLEASE HELP!! MIGHT GIVE BRAINLIEST!!!!! Graph a line with x - intercept of -2 and has a slope of 3
(Economics) Which of the following best explains why the money supply is increased when the Fed buys Treasury bonds? A. When the Fed buys Treasury bonds, it inc
if a−b=5 and ab=75 find the value of a2+b2​
please find the value of x
Set up the ratio for cos(A)
Zeke's Soda is a small company. They have never grown much, but they have never quite gone out of business over their 75 year history.They have a secret recipe
Hello I need help please
Trong các phương trình sau, phương trình bậc nhất một ẩn là: A. x+x2=0 B.+1=0 C. x-2=0 D.(x+3)(2x-1)=0