If 10 men can complete a piece of work in 30 days how many men are requiredto complete the same job in 25 days?

Respuesta :

AL2006
AL2006 AL2006
  • 22-07-2014
We must assume that all workmen work at the same rate, and keep it up forever.

More men ==> fewer days

so the proportion is:    30/25 = x/10

Cross-multiply the proportion:

300 = 25 x

Divide each side by 25 :

x = 300/25 = 12 men
Answer Link

Otras preguntas

Aisha bought 15 apples and oranges for $9. 0. Each orange costs $0. 50, and each apple costs $0. 65. Let x represent the number of oranges and y represent the n
Help help help history
Globalization and imperialism are two side of the same coin?
Geographers consider the areas stretching above and below the Sahara Desert as part of the African continent. Some geographers feel the cultures of North Africa
Help help ASAP ASAP
Marty was renting a boat and wanted to get the best plan. Rental plan A charges a fee of $50 plus $25 per hour. Plan B charges a fee of $10 plus $35 per hour. U
Shirt Circuit Graphic Tees has fixed expenses of $25,560 for the production of their t-shirts. They have a variable expense of $4.50 for each t-shirt that they
A data analyst uses the color tool in tableau to apply a color scheme to a data visualization. In order to make the visualization accessible for people with col
Kari needs to change the brightness and contrast on an image she has inserted into a Word document. Which group should she use to do this? Adjust Picture Styles
in the diagram m∠UYF= 42 1/8What is ∠FYT?